Xcel Energy Northeast Metro Natural Gas Project

Xcel Energy 2019 Gas Project

Project Overview

Xcel Energy will replace approximately eight miles of natural gas infrastructure in Ramsey County. The Northeast Metro Natural Gas Project will be constructed as part of our commitment to system revitalization.

This project will begin at Century Avenue N., south of Larpenteur Avenue, and end at County Road B and Rice Street. The project begins and ends at existing natural gas facilities at these locations.

Project Schedule

Construction activities will occur the following dates:

  • Century Avenue, N., south of Larpenteur Avenue, to County Road B and White Bear Avenue—May 2019 through November 2019
  • County Road B and White Bear Avenue to County Road B and Rice Street—May 2020 through November 2020

The anticipated completion of the project, including restoring work areas and bringing the project into service, in fall 2020.