2020 McKnight Improvement Project

On September 17, 2019 the City Council authorized the advertisement for bids for the CSAH 68 (McKnight Road) Intersection Improvements (City Project No. C.P. 19-02; S.A.P. 151-020-033 / 151-268-001 / 062-668-057). Improvements proposed as part of the project include the following:
Bituminous paving, signal construction, signing, storm water management, utility construction, and construction of Anchor Drive.

The Mayor and City Manager authorized and directed to enter into a construction contract with Rachel Contracting, LLC in the name of the City of North St. Paul for the improvement of the CSAH 68 (McKnight Road) Intersection Improvements (City Project No. C.P. 19-02; S.A.P. 151-020-033 / 151-268-001 / 062-668-057) in the amount of $2,185,876.70.