McKnight Improvement Project

Closure Map and Detour for McKnight Road

On September 17, 2019 the City Council authorized the advertisement for bids for the CSAH 68 (McKnight Road) Intersection Improvements (City Project No. C.P. 19-02; S.A.P. 151-020-033 / 151-268-001 / 062-668-057). Improvements proposed as part of the project include the following:
Bituminous paving, signal construction, signing, storm water management, utility construction, and construction of Anchor Drive.

The Mayor and City Manager authorized and directed to enter into a construction contract with Rachel Contracting, LLC in the name of the City of North St. Paul for the improvement of the CSAH 68 (McKnight Road) Intersection Improvements (City Project No. C.P. 19-02; S.A.P. 151-020-033 / 151-268-001 / 062-668-057) in the amount of $2,185,876.70.

Road Closure Notice for Monday, June 29

McKnight Road will be closed to all traffic Monday, June 29 from 7:00 p.m. until 7:00 a.m. from County Road B to Hwy 36 for sewer installation work. 

Anticipated Work Scheduled for the week of June 29- July 2 

  • Storm sewer install across McKnight will take place on Monday night
  • Grading of the roadway to take place most of the week
  • Curb and Gutter to take place middle of next week

Anticipated Work Scheduled for the week of July 6 – July 10 

  • Paving of west side of McKnight and Castle Avenue
  • Signal work will continue
  • Grading for walks and trails
  • Schedule will be weather dependent of planned work

Connect with us

To stay up to date, and get the latest information, join the project email list. projects@northstpaul.org 

Project hotline
(651) 747-2485

Jason Kiser,
City Construction Representative:
(612) 499-2585 

Morgan Dawley, City Engineer:
(651) 286-8476

Public Works After Hours Hotline: (water, sewer, electric outages)
(651) 747-2417

In case of an emergency call 911